View Details
| Bid Classification: |
Construction
|
|---|---|
| Bid Type: | RFP |
| Bid Number: | 789123 |
| Bid Name: | 789123-RFP-2024-EWSI-9L-AB-Edmonton-DA-Trunk #94 Rehab -CMAR |
| Bid Status: | Closed |
| Bid Closing Date: | Wed Oct 2, 2024 2:00:59 PM (MDT) |
| Question Deadline: | Wed Sep 25, 2024 2:00:00 PM (MDT) |
| Duration in months: | 60 |
| Negotiation Type: | Refer to document |
| Condition for Participation: | Refer to document |
| Electronic Auctions: | Not Applicable |
| Language for Bid Submissions: | English unless specified in the bid document |
| Submission Type: | Online Submissions Only |
| Submission Address: | Online Submissions Only |
| Public Opening: | No |
| Description: |
The intent of this RFP is to find a Successful Proponent capable of providing the Work described immediately below. A more detailed description of the Work can be found in Appendix 1 (Information).
A more detailed description of the Work can be found in Appendix 1. The Project will be delivered using the methodology of Construction Management at Risk (CMAR). As such, the project is broken into two parts for the Construction Manager:
The goals of a CMAR is for the Owner, Consultant, and Construction Manager to establish a collaborative, efficient and high performing team which meets the Project objectives and Milestones. Choosing a Construction Manager early in the design stage is the one key step in meeting these goals. During the Project, the Construction Manager is to provide advice and feedback on constructability, cost and schedule as outlined in Section 2.1.1 of Schedule A. When design of the facility has progressed to the level of detail deemed acceptable to the Owner, the Construction Manager will be presented with the drawings and specifications available and requested to provide the Owner with a Guaranteed Maximum Price (“GMP”) as outlined in Schedule F of the Contract. Only a portion of the Services will initially be contracted for. The performance of subsequent portions of the Services is not guaranteed. The subsequent portions of the Services may become involved if requested by the Owner or if an agreement is reached between the parties, as applicable. Likewise, the performance of the Construction Work by the Construction Manager is not guaranteed. If an agreement is made between the Owner and the Construction Manager, the Construction Manager will also complete the Construction Work. |
| Bid Document Access: | Bid Opportunity notices and awards and a free preview of the bid documents is available on this site free of charge without registration. Please note, some documents may be secured and you will be required to register for the bid to download and view the documents. There is no cost to obtain an unsecured version of the document and /or to participate in this solicitation. |
| Trade Agreements: |
Show Trade Agreements [+]
Canada-European Union Comprehensive Economic and Trade Agreement (CETA)
None Canadian Free Trade Agreement (CFTA) Canada-UK Trade Continuity Agreement (Canada-UK TCA) |
| Categories: |
Show Categories [+]
|
Meeting Locations
The following are the meeting times and locations for the bid: